Final check — Building Maintenance Planning and Contractor SLA Management

Answer the 24 questions. You need 80% or more to pass. You can retry as many times as you like.

Study the course →

Question 1In EN 13306 terms, what is condition-based maintenance?
Question 2A store-room light fitting fails. It is cheap, quick to replace and nobody relies on it for safety. Which strategy suits it best?
Question 3You score assets 1-3 on safety/legal impact, business impact and cost to restore. A sprinkler pump scores 3, 2 and 3. How should it be treated?
Question 4Which source is the best starting point for building an asset register in a recently completed building?
Question 5In what order should the three layers of a PPM plan be built?
Question 6The annual fire alarm service report lists three faulty detectors. The visit is marked complete in the PPM tracker. What is still missing?
Question 7Your calendar puts the annual chiller service in August, the hottest month, and the boiler service in January. What should you change?
Question 8What is SFG20, used in many UK maintenance contracts?
Question 9A draft contract says the contractor will maintain “all mechanical plant” with no schedule attached. What is the main risk?
Question 10For reactive repairs, which pricing model is usually most suitable?
Question 11A fault is reported at 16:50 on Friday. The SLA gives P3 jobs 2 working days but does not say whether the clock runs at weekends. What is the problem?
Question 12The emergency lighting fails across a stairwell at night. Under a typical SLA matrix, how should the helpdesk log it?
Question 13According to HSE UK guide INDG368, who has health and safety responsibilities when a contractor works on your premises?
Question 14In France, an outside company will spend about 600 hours a year maintaining your HVAC plant. What does the Code du travail require?
Question 15A plumber arrives to work in a ceiling void of a 1970s building. The asbestos register shows asbestos insulation board in that area. What should happen first?
Question 16Which tasks normally need a permit to work before a contractor starts?
Question 17Occupants often email the contractor’s engineer directly to report faults, and he fixes them without logging anything. What is the main problem?
Question 18Who should close a reactive work order once the repair is done?
Question 19An insurer asks for proof that your emergency lighting was tested last year. The contractor says the records are in its own system, which you cannot access. What should you change?
Question 20Under the Fire Safety (England) Regulations 2022, how often must communal fire doors be checked in a block of flats over 11 m?
Question 21What is the difference between an SLA and a KPI?
Question 22The contractor’s scorecard shows 100% PPM completion. Your spot check of five closed PPM orders finds two filters that were not changed. What should you do?
Question 23Late fixes are partly caused by your own security team taking two days to approve contractor access. What is the fair response?
Question 24Which feature makes a service credit regime work well?