Final check — Earned Value Management and Project Risk, with Worked Calculators

Answer the 24 questions. You need 80% or more to pass. You can retry as many times as you like.

Study the course →

Question 1Which statement best describes earned value (EV)?
Question 2A work package has a budget of 40 k. It is measured as 25% complete and 15 k has been spent on it. What is its EV?
Question 3You are setting earning rules. The project administration package (document control, meetings) has no measurable output. Which rule fits it?
Question 4Reporting is monthly. A task of about two weeks starts and finishes inside one period. Which earning rule is simplest and still objective?
Question 5At month 5: BAC 120 k, PV 60 k, EV 54 k, AC 48 k. What is the cost variance?
Question 6Same project: PV 60 k, EV 54 k, AC 48 k. What is the SPI?
Question 7A project shows CPI 1.10 and SPI 0.85. What does this mean?
Question 8A project finished three months late, yet its final SPI is exactly 1.00. A manager says “so we were on schedule”. What is the correct explanation?
Question 9BAC 400 k, EV 160 k, AC 200 k. The team expects current cost efficiency to continue. What is the EAC?
Question 10Same figures (BAC 400 k, EV 160 k, AC 200 k). The whole overrun came from a one-off flood repair, now closed, and the remaining work is running to budget. Which EAC is most defensible?
Question 11BAC 400 k, EV 160 k, AC 200 k. The sponsor insists on finishing within the original budget. What TCPI does the remaining work need?
Question 12What does the estimate to complete (ETC) represent?
Question 13In a risk workshop, four entries are proposed. Which one is a well-formed risk statement?
Question 14Yesterday the main tower crane broke down and lifting has stopped. Where should this be recorded and managed?
Question 15How does ISO 31000:2018 define risk?
Question 16Large transformers will be shipped by sea. The team buys cargo insurance and adds a damage clause to the freight contract. Which threat response is this?
Question 17A threat has a 20% probability and an impact of 150 k. What is its expected monetary value?
Question 18An estimator gives three durations for commissioning: optimistic 6, most likely 9, pessimistic 18 days. What is the PERT mean?
Question 19In PMI terms, what is the management reserve for?
Question 20Option A costs 50 k up front with a 10% chance of a 200 k failure. Option B costs 20 k with a 30% chance of the same failure. Which has the lower expected cost?
Question 21The performance-based EAC is 900 k. Open threats total an EMV of −60 k and open opportunities +15 k. What risk-adjusted EAC should you report?
Question 22For four months the piping package has shown a negative CV caused by weld rework. The variance report says only “rework, monitoring”. What should the controller push for?
Question 23BAC is 1 M. AC is 600 k and EV is 450 k. The site manager wants the board report to say “60% complete”. What should the report say?
Question 24How many guidelines does the ANSI/EIA-748 standard for earned value management systems contain?