AMAADOR ACADEMYCertificatesVerify a certificate

AUDSK

Final check — ISO 19011 Audit Skills: Planning, Interviewing and Writing Nonconformities

Answer the 24 questions. You need 80% or more to pass. You can retry as many times as you like.

Study the course →

Question 1In ISO 19011:2018, what is audit evidence?
Question 2An automotive customer sends two of its auditors to check your plant against its supplier quality manual. What type of audit is this?
Question 3Before the report is issued, a production manager asks the internal auditor to drop a well-evidenced nonconformity because "it will cost the team its quarterly bonus". Which response follows the principles of auditing?
Question 4Which principle of auditing was added in the 2018 edition of ISO 19011?
Question 5What is an audit programme?
Question 6You manage an internal audit programme. The welding line had a serious nonconformity last year and a new legal requirement now applies to it. Other processes are stable. Which process should be audited first?
Question 7Two weeks before an audit, the auditee says the key maintenance records are held by a contractor and will not be available on the audit dates, and half the team will be on leave. What should the team leader do?
Question 8Your team in Paris must audit a supplier’s purchasing process in Riyadh. You plan to review records by shared screen and interview the buyer by video. Is this acceptable under ISO 19011:2018?
Question 9Which item belongs in the audit plan rather than in the audit report?
Question 10A colleague’s checklist for the purchasing audit has one line: "Suppliers evaluated? Yes / No". The audit slot is one hour. What is the most useful improvement?
Question 11An audit client wants a statement, with a stated confidence level, about the error rate in 2,000 similar supplier invoices. Which sampling method fits?
Question 12You are building the timetable for a one-day audit of a cable manufacturing plant. Which approach tests the system best?
Question 13During a quality audit walk-round, you see an operator cleaning a running conveyor with its guard removed. What should you do?
Question 14What is the role of an observer during an audit?
Question 15A goods-in supervisor tells you: "Every incoming lot is inspected before it goes to stock." How do you turn this into audit evidence?
Question 16An hourly check sheet shows identical values in the same handwriting for a whole 8-hour shift. The operator says he fills it in at the end of the shift. What does this indicate?
Question 17Which of these is a leading question that an auditor should avoid?
Question 18Your audit scope includes the night-shift packing team. When and where should you interview them?
Question 19Halfway through an interview, a storekeeper says angrily: "Are you here to get me fired?" What is the best response?
Question 20You have finished questioning a maintenance planner. What should you do before leaving?
Question 21What are the three parts of a well-written nonconformity statement?
Question 22You found that gauge G-7, in use on line 2, was three months past its calibration due date. Which nonconformity wording is best?
Question 23After a nonconformity on a missed interlock test for press P3, the maintenance team tests P3 the same afternoon and records it. What is this action?
Question 24At the closing meeting, the plant manager accepts the facts of a finding but strongly disagrees with its grading. Discussion does not resolve it. What should the team leader do?