الاختبار النهائي — كانبان للفرق باستخدام Jira: التدفق وحدود العمل الجاري والمؤشرات

أجب عن الأسئلة الـ24. تحتاج إلى 80% أو أكثر للنجاح. يمكنك إعادة المحاولة كلما أردت.

هذا الاختبار النهائي متاح بـالإنجليزية.

ادرس الدورة ←

السؤال 1How does the Kanban Guide for Scrum Teams (Scrum.org) define Kanban?
السؤال 2A colleague says Kanban means ‘people take new work whenever a manager assigns it’. What is wrong with this?
السؤال 3Which of these is one of the Kanban Method’s change management principles (Kanban University)?
السؤال 4Your team uses Scrum and wants to add Kanban. Which source is written for exactly this situation?
السؤال 5Two team members measure cycle time differently: one from ticket creation, the other from the first commit. What should the team do?
السؤال 6Which element is part of a Definition of Workflow according to the Kanban Guide for Scrum Teams?
السؤال 7A manager proposes one board column per team member so everyone sees ‘who has what’. What is the main risk?
السؤال 8Why split a step such as Develop into ‘doing’ and ‘done’ sub-columns?
السؤال 9Test has a WIP limit of 2 and holds 2 items. A developer finishes an item and is free. What is the best action?
السؤال 10Average throughput is 4 items per week and average WIP is 12. By Little’s Law, average cycle time is about:
السؤال 11Cycle times have doubled over two months while throughput stayed flat. According to the Kanban Guide for Scrum Teams, what should the team try first?
السؤال 12Your team breaks its WIP limit almost every day because ‘urgent’ requests arrive. What is the most useful response?
السؤال 13Which flow metric applies only to items that are still in progress?
السؤال 14A stakeholder asks when a newly started item will be done. Your SLE is ‘85% of items within 12 days’. What is the best answer?
السؤال 15What is throughput in the Kanban Guide for Scrum Teams?
السؤال 16At the daily meeting, which item should the team discuss first?
السؤال 17In Jira, the In Progress column header has turned red. What does it mean?
السؤال 18A team member applies the quick filter ‘Only my items’ and says Review is under its limit. Is this reliable?
السؤال 19On a Jira board, which column counts work items as complete?
السؤال 20Your team keeps many raw ideas on the board, which clutters the first column. Which Jira feature helps most?
السؤال 21In Jira’s cumulative flow diagram, the Test band has widened steadily for a month. What does it most likely show?
السؤال 22In Jira’s control chart, what decides whether you see cycle time or lead time?
السؤال 23At a retrospective, the team wants to change columns, WIP limits and card types all at once. What is the main risk?
السؤال 24A Scrum team using Kanban wants to decide how much to take into the next Sprint. What does the Kanban Guide for Scrum Teams suggest?