Final check — PRINCE2 7 Foundation Exam Prep

Answer the 42 questions. You need 80% or more to pass. You can retry as many times as you like.

Study the course →

Question 1The PRINCE2 7 Foundation exam has 60 questions and a 60% pass mark. How many correct answers are needed to pass?
Question 2Amina has ten minutes left in her Foundation exam and eight questions she is unsure about. What is the best use of her time?
Question 3A hotel group in Marrakech runs daily housekeeping and is also refurbishing its lobby by March. Which characteristic makes the refurbishment a project rather than business as usual?
Question 4Which of these is NOT one of the five integrated elements of PRINCE2 7?
Question 5A project to introduce a new rota system in a Jeddah hospital worries about how nurses will accept the change and how leaders will communicate it. Which integrated element addresses this most directly?
Question 6Which of these does PRINCE2 7 treat as a performance target alongside time, cost, quality, scope, benefits and risk?
Question 7Before planning a new branch opening, the project manager reads the reports of the last three branch openings and talks to their managers. Which principle is she applying?
Question 8A project board in Abu Dhabi approves funding for stage 2 only, based on a detailed stage 2 plan, and says it will decide on stage 3 later. Which principle does this show?
Question 9A project manager has a stage cost tolerance of plus or minus 5%. A small overspend of 2% is forecast, and she handles it without calling a board meeting. Which principle allows this?
Question 10Which statement about the PRINCE2 principles is correct?
Question 11Before a training video is filmed, the team agrees in writing its purpose, length, languages and the checks it must pass. Which principle is being applied?
Question 12A company says it uses PRINCE2 but has decided that internal projects under a certain size will not have any business case. What is the correct view?
Question 13Who owns the business case and is ultimately accountable for the project?
Question 14On a project to build a new website, the board member from the web agency commits designers and is accountable for the quality of what the agency delivers. What is this role?
Question 15At a board meeting, the senior user and the senior supplier disagree about whether to delay a release. Who makes the final decision?
Question 16Which combination of roles does PRINCE2 NOT allow?
Question 17A busy project board wants a small group of users to approve minor requests for change up to a set budget, without a full board meeting. What should the board appoint?
Question 18A small municipal project in Agadir has no one appointed to project support. Who carries out project support activities?
Question 19A project delivers a new customer-service system. Staff now log all calls in it, and six months later complaints have fallen by 20%. Which of these is a benefit?
Question 20In which process is the outline business case first prepared?
Question 21Two years after a new warehouse system went live, the company wants to know whether the promised reduction in picking errors has been achieved. Who is accountable for showing that this benefit was realised?
Question 22Which level of plan is optional in PRINCE2?
Question 23Rachid has written the project product description for a new staff handbook and has just broken it down into its component products. What is the next step of product-based planning?
Question 24A four-stage project is in stage 2. When should the detailed plan for stage 3 be produced?
Question 25Where are the customer's quality expectations first recorded?
Question 26At a quality review of a draft procedure, the reviewers have raised their points. Who decides whether the product is complete, conditionally complete or incomplete?
Question 27An auditor asks to see the detailed test results for a product. The quality register shows the test took place and passed. Where should the detailed results be?
Question 28A project team in Riyadh is writing its risk register. Which entry is written in the cause, event, effect form PRINCE2 recommends?
Question 29A supplier offers a 10% discount if equipment is ordered before 1 May. The project manager reorganises the plan so the order is certain to be placed in April. Which opportunity response is this?
Question 30In the risk register, each risk names one person who is accountable for managing it and making sure the agreed responses happen. What is this person called?
Question 31During testing, a supplier warns that the new payroll system will not meet the 2-second response time written in its product description. What type of issue is this?
Question 32Users ask for an extra management dashboard that was not in the agreed scope. No change authority has been appointed. Who decides whether to approve it?
Question 33Who sets the tolerances for a management stage?
Question 34Every Friday, the team manager building a training portal sends the project manager a short report on progress against the work package. What is this report?
Question 35After reading an exception report, the project board decides the project is still justified but the current stage plan cannot be achieved. What should it ask the project manager for?
Question 36Which of these is a time-driven control?
Question 37What triggers the starting up a project process?
Question 38The board has just authorized initiation of a new clinic project in Fès. In which process will the project initiation documentation be assembled?
Question 39A team manager meets the project manager to agree the products, tolerances and reporting for a piece of work before starting it. Which process is the team manager carrying out?
Question 40At the end of which stage is managing a stage boundary NOT normally used?
Question 41A new law makes a planned mobile app illegal, and the project board instructs the project to stop. What should the project manager do next?
Question 42A software team in Casablanca works in two-week agile sprints. The organization wants to run the overall project with PRINCE2. How does PRINCE2 fit?