الاختبار النهائي — التحضير لامتحان PSM II: Professional Scrum Master II

أجب عن الأسئلة الـ42. تحتاج إلى 85% أو أكثر للنجاح. يمكنك إعادة المحاولة كلما أردت.

هذا الاختبار النهائي متاح بـالإنجليزية.

ادرس الدورة ←

السؤال 1According to Scrum.org, what is the pass mark for the PSM II assessment?
السؤال 2Which statement about the PSM II assessment format is correct, according to Scrum.org?
السؤال 3A team's burndown chart always looks perfect. You learn that Developers update it at the end of each day to match the plan, not the actual remaining work. Which empirical pillar is most damaged?
السؤال 4In a Retrospective, a Developer admits she merged code without tests to meet the Sprint Goal. Others look away and the room goes quiet. Which Scrum Master response best supports the Scrum values?
السؤال 5A sponsor asks for a detailed 12-month plan with fixed scope, date and cost for a new product in an unknown market. How should the Scrum Master help?
السؤال 6According to the 2020 Scrum Guide, what is Scrum founded on?
السؤال 7Halfway through the Sprint, a competitor's launch makes the Sprint Goal irrelevant. The Developers want to keep going because the work is nearly finished. Who can cancel the Sprint?
السؤال 8A team says its Daily Scrum is boring and wants to hold it only on Mondays and Thursdays. What should the Scrum Master do?
السؤال 9Which commitment belongs to the Increment?
السؤال 10At the Sprint Review, the Product Owner wants to show two items that pass functional tests but have not been through security review, which the Definition of Done requires. What is correct?
السؤال 11Four Scrum Teams build one product. Each has its own Product Backlog and its own Definition of Done. Integration problems appear at every release. What is the most important change?
السؤال 12When is an Increment born, according to the 2020 Scrum Guide?
السؤال 13A line manager attends every Daily Scrum and asks each Developer what they did yesterday. Developers now report to him instead of planning together. What should the Scrum Master do first?
السؤال 14Two senior Developers argue strongly about the architecture of a new module. The debate has gone on for two days and the team is waiting. What is the Scrum Master's best move?
السؤال 15According to the 2020 Scrum Guide, what does self-managing mean for a Scrum Team?
السؤال 16In every Retrospective, one confident Developer speaks first and the others mostly agree with him. What is the best facilitation change?
السؤال 17A new team is in a tense phase: members disagree openly about working agreements and some are frustrated. Management asks the Scrum Master to stop the conflict. What should the Scrum Master consider?
السؤال 18Only one Developer knows how to deploy the product. She is going on leave for a month. What should the Scrum Master encourage?
السؤال 19A team new to Scrum asks why they cannot add a 'testing Sprint' after every two development Sprints. Which stance fits best first?
السؤال 20How does the 2020 Scrum Guide describe Scrum Masters?
السؤال 21A Developer tells you she feels stuck in her career and wants to become a better facilitator. She asks for your help. What is the most fitting approach?
السؤال 22A team knows Scrum well, yet keeps missing its Sprint Goals. They ask the Scrum Master what to change. Which response is most coaching-oriented?
السؤال 23You see the team about to adopt a small, reversible branching rule you expect will cause some merge pain. No customer impact is possible. What could a Scrum Master reasonably do?
السؤال 24Which behaviour is a misunderstood Scrum Master stance rather than a helpful one?
السؤال 25Stakeholders keep sending requests directly to Developers, who add them to the Sprint without telling the Product Owner. What should the Scrum Master do?
السؤال 26A Product Owner reports success only as the number of items delivered each Sprint. Customers are not using several new features. How can the Scrum Master help?
السؤال 27Which of these is one of the four Key Value Areas in Scrum.org's Evidence-Based Management guide?
السؤال 28A large client sends a committee of five people who each tell the team what to build. The named Product Owner just passes their requests on. What is the core problem?
السؤال 29A stakeholder asks the Scrum Master for a firm date when the next major feature set will ship. What is the most professional response?
السؤال 30The Sprint Review has become a slide presentation for managers. No users attend and the Product Backlog never changes afterwards. What should the Scrum Master suggest?
السؤال 31Before each release, the team holds a two-week stabilisation phase to fix bugs. What does this most likely show?
السؤال 32Who should decide which engineering practices, such as test-driven development, a Scrum Team uses?
السؤال 33The Product Owner asks the Developers to skip writing automated tests for a month to reach a trade show. The Developers are uneasy. What should the Scrum Master do?
السؤال 34In the Nexus framework, what is the Nexus Integration Team accountable for?
السؤال 35A team's velocity has dropped for six Sprints. Developers say the code is hard to change. Management proposes adding three people. What should the Scrum Master point out?
السؤال 36Deployment is a manual, 40-step checklist done by one person late at night. Last release, a missed step caused an outage. What should the Scrum Master encourage first?
السؤال 37Developers are each assigned to three different teams at 33% each. Focus is low and Sprint Goals are often missed. What is the Scrum Master's best action?
السؤال 38The team cannot release because a separate QA department tests only once a month. What is the most useful longer-term action?
السؤال 39Which is one of the Scrum Master's services to the organisation, according to the 2020 Scrum Guide?
السؤال 40A CEO wants all 40 teams to switch to Scrum on the same day next month, with a fixed transformation end date. How should the Scrum Master advise?
السؤال 41A department manager asks what his role is now that the teams are self-managing. What is the most helpful answer?
السؤال 42Teams are split by technical layer: front end, back end and database. No team can deliver a feature alone. What change would most improve delivery?