الاختبار النهائي — التحضير لامتحاني SAFe POPM وSAFe Scrum Master (SAFe 6، إصدار الذكاء الاصطناعي)

أجب عن الأسئلة الـ42. تحتاج إلى 82% أو أكثر للنجاح. يمكنك إعادة المحاولة كلما أردت.

هذا الاختبار النهائي متاح بـالإنجليزية.

ادرس الدورة ←

السؤال 1According to Scaled Agile's SSM page, what is the format of the SAFe Scrum Master exam?
السؤال 2Which SAFe core value is most directly at stake when a team hides a failing build from the System Demo?
السؤال 3A director wants each team to choose its own iteration length so they can 'optimise locally'. Which SAFe principle does this most clearly conflict with?
السؤال 4A Scrum team moving onto an ART asks what replaces its Daily Scrum. What is the SAFe name for this event?
السؤال 5Who is the chief facilitator of ART events such as PI Planning and Inspect and Adapt?
السؤال 6A new SAFe team asks how many people it should have. Which answer fits SAFe guidance for an Agile team?
السؤال 7Who owns and prioritises the ART backlog?
السؤال 8A PO has rewritten the team's roadmap to promise a fixed date for every feature two years out. What is the main problem?
السؤال 9What does a well-written feature include besides its short name and description?
السؤال 10A team has delivered only new features for three PIs and the build now takes a full day. Which backlog item type should the PO and PM make room for?
السؤال 11A PM and a PO disagree about how a feature should be split into stories for the team. Who normally leads the split into stories?
السؤال 12A PO plans a feature using only requests from internal stakeholders and has never spoken with end users. What SAFe practice should she add first?
السؤال 13During team sync, two developers start debating a database design in detail. The sync is already at 14 minutes. What should the SM/TC do?
السؤال 14Which description best fits the SAFe Scrum Master/Team Coach?
السؤال 15A team is blocked because a shared test environment owned by another ART is down. The team cannot fix it. What should the SM/TC do?
السؤال 16A newly formed team argues often about coding standards and roles. In Tuckman's terms, which stage is it most likely in, and what helps?
السؤال 17The team's retrospectives produce the same complaints every time and nothing changes. What should the SM/TC try first?
السؤال 18A team member asks the SM/TC how to estimate a story. What is the best coaching response?
السؤال 19How is WSJF calculated in SAFe?
السؤال 20Feature A: CoD 24, size 8. Feature B: CoD 15, size 3. Feature C: CoD 30, size 13. In what WSJF order should they be done?
السؤال 21Which three components make up Cost of Delay in SAFe's WSJF?
السؤال 22During PI Planning, a team's objective has a key dependency on a vendor that may not deliver. The team still wants to include the objective. How should it be planned?
السؤال 23In ROAM, what does it mean when a risk is 'Owned'?
السؤال 24At the end of PI Planning day 1, several teams report they cannot fit the top features with the people available. Where are these issues mainly addressed?
السؤال 25In the 3Cs of a user story, what does 'Confirmation' refer to?
السؤال 26A new team of five full-time developers and testers starts its first iteration. One person has two days of holiday. Using SAFe normalised estimating, what is a reasonable starting capacity?
السؤال 27A story 'Customer can pay by card, transfer or wallet' is too big for one iteration. Which split is most in line with SAFe guidance?
السؤال 28A manager wants to compare velocity across teams to find the 'most productive' one. What should the Scrum Master explain?
السؤال 29The PO plans to review and accept all stories on the last afternoon of the iteration. What is the better practice?
السؤال 30A team's Kanban board shows ten items in testing and the testers are overwhelmed, while developers keep starting new stories. What should the team do first?
السؤال 31What are the three parts of the Inspect and Adapt event?
السؤال 32A team planned committed objectives worth 20 business value points. Business Owners scored actual value at 15 for those, plus 3 for an uncommitted objective delivered. What is the team's predictability?
السؤال 33Each team shows its own work in its iteration review, but the ART's System Demo shows slides because the parts are not integrated. What is the main risk?
السؤال 34Which activity is NOT an intended use of the Innovation and Planning iteration?
السؤال 35A feature is deployed to production behind a toggle, but marketing wants to launch it next month. Which statement is correct?
السؤال 36Midway through the PI, two teams discover a new dependency that threatens a committed objective. Where is it best raised so PMs and POs can adjust scope?
السؤال 37A PO asks an AI tool to rank the ART backlog and plans to publish the ranking as is. What should she do?
السؤال 38An AI assistant produces a market summary for a feature, quoting three studies the PM cannot find anywhere. What is the right action?
السؤال 39A Scrum Master wants to paste the team's full retrospective chat, with names, into a public AI chatbot to find themes. What is the main concern?
السؤال 40What do both AI-Empowered course pages say about AI-generated strategic insights?
السؤال 41An AI tool drafts 30 stories from one feature. Most split the work by layer (UI, API, database). What should the PO do?
السؤال 42A manager wants the SM/TC to use flow data and an AI tool to rank team members by tickets closed. What fits SAFe values best?